Detours coming to Van Buren Street in East Falls Church neighborhood, potentially as soon as Oct. 2 and lasting until March 2018. Construction technically in City of Falls Church.
Will affect thru-riders on W&OD.
Project Page: http://www.fallschurchva.gov/1568/Van-Buren-Bridge
Text of official letter to nearby residents:
September 14, 2017
Subject: VAN BUREN BRIDGE CONSTRUCTION
Dear Resident:
The City of Falls Church Department of Public Works will begin the replacement of Van Buren Bridge in the first week of October 2017. Our current construction schedule has access across the bridge shut down starting October 16th, 2017. Given the large scope of the project we anticipate the bridge will be closed till the end of March 2018. This closure is required as the entire bridge will be removed and rebuilt. Marked detours will be set up, routing vehicular, pedestrian, and bicycle traffic around the work zone.
Construction will typically occur on weekdays from 7 A.M. to 5 P.M. and may include some weekend work, dependent on weather impacts. As with most construction projects, nearby residents can expect inconveniences such as noise, dust, and construction traffic.
Residents will have access to driveways and entrances during this time period.
More information on this project, as well as project updates, are available at the City’s project website: http://www.fallschurchva.gov/1568/Van-Buren-Bridge
If you have concerns or questions at any time please call James Mak at 703-248-5105 or via email at jmak@fallschurchva,gov. In the event of an emergency outside of business hours please call the City of Falls Church Police non-emergency line at 703-241-5053 (TTY 711).
Sincerely,
James Mak
CIP Engineering Manager
Department of Public Works
City of Falls Church