Custis Trail Work (1/26/17)
- This topic has 4 replies, 4 voices, and was last updated 8 years, 5 months ago by .
-
Topic
-
From my inbox:
“There is a collapsed sanitary sewer pipe behind Saint Ann Catholic School ( 980 N. Frederick St ) near the bike/pedestrian trail (Custis Trail). Our Contractor Sagres Construction will be performing the emergency work. We will be closing the westbound line on the trail and users will have to share the east bound line on the trail. We will put up work ahead signs and lane closure sign on the trail. We are tentatively planning to start on Thursday 1/26/2017 and plan to be completed in 1 week time.”
Viewing 4 replies - 1 through 4 (of 4 total)
Viewing 4 replies - 1 through 4 (of 4 total)
- You must be logged in to reply to this topic.