Bike Unfriendly Curb Cut on Walter Reed Project
Our Community › Forums › Road and Trail Conditions › Bike Unfriendly Curb Cut on Walter Reed Project
- This topic has 72 replies, 22 voices, and was last updated 5 years, 9 months ago by
zsionakides.
-
AuthorPosts
-
February 28, 2019 at 3:08 am #1096163
zsionakides
Participant@dasgeh 187864 wrote:
I’ve been told that curbs like that are almost always about water management and/or soil retention.
Soil retention makes sense for the concrete barrier next to the power line pole, but it doesn’t make sense on the curb cut for the road. If you see the curb cut they build on the southwest corner by the Shell station, it’s wide and easy to navigate for bikes crossing both Walter Reed or Four Mile Run.
February 28, 2019 at 2:10 pm #1096171dasgeh
Participant@zsionakides 187986 wrote:
Soil retention makes sense for the concrete barrier next to the power line pole, but it doesn’t make sense on the curb cut for the road. If you see the curb cut they build on the southwest corner by the Shell station, it’s wide and easy to navigate for bikes crossing both Walter Reed or Four Mile Run.
I’m 100% guessing here, but I would bet that either, the area by the pole is slightly lower than the road, so they (think they) need the curb by the road to keep water from flowing into the sidewalk/bike path/whatever that is; or they think this is such a big area that cars would end up driving on the sidewalk/bike path/whatever that is if there weren’t a vertical barrier (that may even be an ADA thing). As to the water, if the topography is such that the area by the light pole would become a pond without the second curb, then just removing the second curb doesn’t work.
Not excusing the design, but it helps to know what the real issue is to come up with a solution.
March 11, 2019 at 2:35 pm #1096653zsionakides
ParticipantUpdate: This morning when I was running by the intersection and waiting for the light, I saw and overheard five personnel from Arlington discussing the curb cut. A couple of them were not construction workers as they had office wear on under their vest and hardhat. Hopefully this leads to a fix as they were pointing out widening the curb cut and looking at where the pedestrian light is.
April 14, 2019 at 11:31 pm #1097728Judd
ParticipantIt appears that the curb cut has been repoured. It’s still under plastic but it appears that the curb was shortened, making a wider pedestrian landing. It looks like it will be better but still an awkward angle. Sorry that it’s upside down. I’ll try reposting from my phone to see if it will come out right side up.
[ATTACH=CONFIG]19962[/ATTACH]
April 14, 2019 at 11:36 pm #1097729Judd
ParticipantHopefully this posts right side up.
April 18, 2019 at 4:02 pm #1097788zsionakides
ParticipantI didn’t get a pic, but they only fixed the crosswalk part. The chute still exists and the turn is still challenging going eastbound.
On the NE corner, they did it right, and it will be quite easy to navigate.
April 19, 2019 at 12:20 am #1097801Judd
ParticipantA few pics from tonight. The curb and the length of the sidewalk was shortened to align the curb cut with the existing crosswalk.
Sent from my iPhone using Tapatalk
April 19, 2019 at 1:19 pm #1097803dasgeh
ParticipantHow is someone with a kid in a trailer supposed to navigate that?
April 20, 2019 at 3:06 am #1097828KLizotte
ParticipantI live on that corner. At a minimum, there needs to be a curb bump out to slow the drivers down when making a right hand turn. It’s a dangerous intersection and I’m furious that left hand turn signal still haven’t been installed for north-south traffc. Sigh.
April 20, 2019 at 2:13 pm #1097832zsionakides
ParticipantI didn’t get photos, but it looks like the crossing of the slip lane on Arlington Mill Drive to the refuge area will be at road grade and not a raised crosswalk like shown in the project documents. That means the school buses and other trucks who currently don’t stop for pedestrians and bikes can continue their practice without having to slow down in the future.
April 20, 2019 at 7:59 pm #1097837Steve O
Participant@zsionakides 189881 wrote:
I didn’t get photos, but it looks like the crossing of the slip lane on Arlington Mill Drive to the refuge area will be at road grade and not a raised crosswalk like shown in the project documents. That means the school buses and other trucks who currently don’t stop for pedestrians and bikes can continue their practice without having to slow down in the future.
That was also how it was presented to the BAC by the project manager – raised crosswalk.
April 21, 2019 at 1:02 am #1097841chris_s
Participant@zsionakides 189881 wrote:
I didn’t get photos, but it looks like the crossing of the slip lane on Arlington Mill Drive to the refuge area will be at road grade and not a raised crosswalk like shown in the project documents.
I expect that the raised crosswalk will be built the same time that the new refuge island is built (the next construction phase).
April 21, 2019 at 11:47 am #1097845zsionakides
Participant@chris_s 189891 wrote:
I expect that the raised crosswalk will be built the same time that the new refuge island is built (the next construction phase).
When I ran by there yesterday you could see the new curb cut from the Arlington Mill trail side and it went to road level, not raised. The refuge has been shaped out and is in progress.
April 22, 2019 at 2:31 pm #1097855dasgeh
ParticipantI’ve been in contact with the project manager about the WRD/FMR curb cut, and have been told that they’re not done with construction. She’s out of the office now, so I’m not sure if I can get an answer about WRD & AMD.
April 22, 2019 at 5:36 pm #1097863Subby
ParticipantUgh why are we still doing rounded corners in 2019? You are just begging for someone to get crushed.
-
AuthorPosts
- You must be logged in to reply to this topic.