November 10, 2012 at 3:57 pm #955339
chris_s
ParticipantScroll down – the revised concept plan is basically what is going forward. A bunch of us weighed in on the concept plans back in 2011 because it was looking like the “interpretive features” were going to cause pedestrians to congregate on the trail.
November 13, 2012 at 3:00 am #955388dbb
ParticipantTook a look at the revised concept plan. Hoping that the planners are selecting trees that beavers don’t like otherwise the “evergreen buffer” will become dinner. The idea of a “turtle basking station” was kind of neat. Most turtles just use a log or a rock but the turtles at the beaver pond will have basking stations. Sweet!
November 13, 2012 at 3:31 am #955390mstone
Participant@dbb 35672 wrote:
The idea of a “turtle basking station” was kind of neat. Most turtles just use a log or a rock but the turtles at the beaver pond will have basking stations. Sweet!
I think I’m going to start calling my comfy chair the “basking station”.
November 14, 2012 at 7:24 pm #955517chris_s
ParticipantI was flipping through the County’s Capital Improvement Plan looking for something else and ran across a section on the Ballston Beaver Pond. The description there makes it sounds like only the storm water parts of the project are being done now and the “boardwalks, trails and interpretation” will be done Fiscal Year 2021 since the funding they are using for construction right now can only be used to improve storm water runoff. I’ll quote the project description here:
13 Ballston Pond
Project Description
The Ballston Pond was originally designed and constructed as a stormwater detention facility when the I-66 highway was built, to collect and slow down the stormwater runoff from I-66. Over the years, the pond has been filling up with sediments deposited by the stormwater runoff, which slows down when it reaches the pond. Retrofitting the Ballston Beaver Pond is a high priority project in the County’s stormwater management program. The plan that has been designed incorporates features such as boardwalks, trails and interpretation which are unable to be funded through the County’s watershed funds. This project is for the final design and implementation of the trails and boardwalks.November 14, 2012 at 8:46 pm #955527Rootchopper
ParticipantThis is interesting because the National Park Service has been waging a war with beavers on the Mount Vernon Trail north of Slaters Lane for the last year. Whenever the beavers dam up the creek running under the boardwalk there, the Park Service comes along and breaches the dam. I think they pulled the plug on the dam today because water was flowing through a sizeable gap in the dam. I’m sure they have their reasons but I kind of like that area when it’s filled with water.
-